Prepping the second mast and the navigation equipment (testing out very old radar)

Work on the fridge / freezer box is still underway, but a second project has also started this past month. The mizzen (second) mast has been lying in wait for almost 2 years, and the time has finally come to prepare it for painting. Also all the navigation equipment needs to be in order so those can be mounted on this mast. The mast has now been sanded and the first layers of paint (primer and first layer coat) have been applied. The temperature plummeted way blow zero (see pictures of the Seadog in the ice below this post), so painting has come to a hold. But with a little luck we can start painting again next week.


I was lucky enough to get a free (be it, rather old) radar system from a friend of my dad. After some due consideration I decided that if it worked I would install it on the mizzen and not bother buying a new (and very expensive) radar system for now. And lo and behold, after some tinkering and even a little guess-work with the wiring, it seems the system is still operational.

 

Seadog in the ice….

Ice, rain and snow


As you can see there were some snowy days here in the Netherlands. But nevertheless work continued aboard the Seadog.
On the starboard side some of the holes that were made to access the through hull bolts were patched up.  And this time two hose connectors were laminated at starboard and port side at the back of the ship to allow excess rainwater to flow out of that hallow space in the top of the hull. Which are connected right into the drainage pipes underneath the waterline. Also all hoses aboard the entire ship have now have been replaced by new hoses with  stainless steel hose clamps. Plus, the storage lockers at the back of the ship finally got there much-needed cleanup as well.

The building of the custom fridge / freezer has not  halted, but only had some minor progress in favour of the above tasks. All the needed supplies are now aboard, so hopefully more on this subject in the next post.